ARAMCO Upstream Facility DCS Migration
Saudi Aramco · Dhahran, Eastern Province
Challenge
Legacy DCS (15+ years old) across 4 production trains with unsupported hardware, growing cybersecurity risk, and difficulty finding spare parts. Migration required zero unplanned downtime during active production.
PowerSolutions Approach
Phased Siemens PCS 7 migration with parallel-running cutover strategy. Custom migration tools preserved all 14,000 control narratives. FAT completed in 8 weeks; full SIT with zero production interruption.